151020 Newcrest Sept 2015 Quarterly Report
The mill has been shut down while engineers on site work to determine the repairs required Concentrator 2 SAG mill continues to operate at full capacity While concentrator 1 SAG mill is offline excess mine production from Cadia East is being stockpiled on